November 25, 2024
The road at Trailside Townes is paved and the connector to the American Tobacco Trail has been cleared! We are in the midst of finalizing documents and will be taking contracts soon.
June 19, 2024
Paving of Selby Avenue, which will be the main road in the community, is well underway. The installation of underground utilities is complete.
May 15, 2024
Construction has officially begun for Trailside Townes! Clearing and grading is well underway and underground utilities are currently being installed. The next phase will be the paving of Selby Road and is scheduled to start on June 1. Follow along on our blog for more updates to come!